Precautions when using rock wool board


Beijing Hongchang Rock Wool Board Manufacturer shares some important considerations when using rock wool board:

1. When transporting and storing plate-shaped insulation materials, it's essential to protect them from damage, contamination, and moisture. During the rainy season, make sure to cover the materials properly to avoid water exposure or flooding.

2. Insulation work should not be carried out on rainy days. The outer walls and thermal bridges of this project are 1200mm × 600mm × 25mm in size. It’s crucial to ensure that the working environment is dry and suitable for installation.

3. The application time for special polymer bonding agents and surface mortar should be no less than 2 hours. This ensures proper adhesion and long-term performance.

4. Fixing parts should be secured with self-tapping rock bolts and aluminum alloy expansion nails. The tensile strength of each fixing point must be at least 0.6kN. Metal screws used in anchor bolts should be made of stainless steel or treated metal to prevent corrosion. Plastic nails and sleeves should be manufactured from polyamide, polyethylene, or polypropylene, and recycled materials should not be used. Choose appropriate anchor bolts based on the type of base wall, and ensure the effective anchoring depth is no less than 30mm. For rock wool boards, the diameter of the plastic disc should be no smaller than 50mm.

Choosing a reliable rock wool board manufacturer is key to ensuring product quality. Our factory specializes in producing high-quality rock wool boards at competitive prices. Hongchang products have passed all necessary tests and are trusted by many customers.

Our popular products include extruded polystyrene boards, extrusion equipment, rock wool felt, rock wool tubes, and more. All our products are known for their excellent quality and affordable pricing—perfect for your next project!

Visit our official website: [http://Contact Zhao Hongpeng](http://Contact Zhao Hongpeng) Phone: [Mobile] Fax: [Fax] QQ: [QQ] Address: No. 268, Changxingzhuang, Xiaotangshan Town, Changping District, Beijing.



Solar Mounting System For Green House

The Installation of Mounting Unit
1. Make the concrete base according to solution drawing, locate embedded bolts and set out strings by Laser Level to ensure the centers of embedded bolts in the same elevation as accurate as possible on vertical, horizontal direction and at end face.
2. Locate the Anchor Plate on the concrete base and adjust the position according to solution drawing(remove M14 washer,M14 spring washer,and M14 nut if they are connected to embedded bolts now),and then fasten M14 washer, M14 spring washer, and M14 nut with the tightening torque of 60N.m.
3.Take out the Hexagon Bolt Kit with Post B Corrugated Gasket M12x95 and remove its nut, spring washer, one washer, and corrugated gasket. Insert the Post A, B, C in to Anchor Plate according to the Hexagon Bolt Kit with Corrugated Gasket M12x95 drawing and then fix them by two sets of Hexagon Bolt Kit with Corrugated Gasket M12*95. Post C Post A
4.Remove the bolt kits M12*90 from all the Posts and Pre-Assembled Supports and unfold the embedded Supports, fasten them on the Posts by bolt kits M12*90 according to the drawing.

Installation of Rails
1.Please check the length of Beam before place it onto the Pre-Assembled Supports, otherwise extend it with Splice forBeam first. There are 4 self-tapping screws in each side and total 8 self- tapping screws in both sides. We strongly recommend NOT extend the Beams on Preassembled Supports.
2.Before locate the Beams, mark the position of the Beam son the surface of Pre-Assembled Supports with maker pens according to solution drawing for easier installation. Place the Beams on the 55*80 Tube of Pre-Assembled Supports and fix it with C Clamp Kits. Install all the Beams in the same step. The tightening torque will be 20N.m. C Clamp Kit Side Beam(Please arrange 3-4 persons to install when the array is long.)

Installation of Solar Panels
1.Place the panels above the Beam 85, fixing it with Wide End Clamp Kit in the side and Inter Clamp Kit in the middle. Install all the panels in the same steps until complete installation of al panels. Fasten all the bolts with tightening torque of 10N.m.
2.Complete installation, and please inspect and make sure all the bolts are fastened.

Solar Panel Mounting Frames,Solar Panel Mounting Systems,Greenhouse Solar Mounting System,PV Mounting Systems

Hebei Honde Plastic & Metal Co., Ltd. , https://www.foundation-system.com